Here is Room FB 208 (originally named ERP Lab), soon to be renamed to Multi Purpose Computer Lab:
 |
| Room FB 208 (previously named ERP Laboratory) |
Day 1 - 11 July 2011 (9:30 am - 17:00) and here is the initial plan for the next few days (drawn on the white board):
 |
| Electrical Wiring and Ducting Installation Plan |
Here is room FB 208 before installation:
 |
| View from the back of the room |
 |
| View from the front (left) |
The Cable Installation team (Emboy and team are busy bringing in all the materials)
 |
| The Cable Team inspecting the working area |
Logistic (cable, trunking and tools) are now inside the room FB 208:
 |
| Cable, tools and trunking equipments |
Now ... installation time (get to work) ...
 |
| Cutting cable |
 |
| Cutting the trunking |
 |
| Drilling the floor |
Installing trunking and cabling on the table ...
 |
| Installing cable under the table |
 |
| Trunking under the table |
 |
| Installing trunking under the table |
 |
| Enjoying cable installation under the table |
Trunking is almost ready on day 1 ...
 |
| Trunking at the back |
 |
| Trunking at the right side |
 |
| Trunking at the left side |
Day 1 end with Trunking and cable under the table ready ...